ENGINEERING & CONSULTANCY
PROJELERİMİZ
Siemens Dolwin4 Borwin4 Facilities
Lingen / Germany
2023-2024
On behalf of Convex ZT GmbH, MARTE contributed to the architectural by Revit and engineering design by Dlubal RFEM per Eurocode of various sub/superstructures (5.000m2), ensuring robust and efficient project execution at the LP5 level according to HOAI standards.
Convex, Siemens
GET H2 Nucleus
Lingen / Germany
2022-2023
Involved in the comprehensive architectural by Revit and engineering design by Dlubal RFEM of multiple sub/superstructures (11.300m2) per Eurocode, applying advanced techniques for optimal results at the LP5 level according to HOAI standards.
Convex, RWE, Envi Con
Gas İşleme Kompleksi GPC (Ust-Luga yerleşkesi)
Leningrad Bölgesi / Russia
2023
SNIP standartlarına göre çeşitli boru-kablo tavası köprülerinin yapısal mühendislik tasarımına katkıda bulunulmuştur.
Rönesans, Gazprom Linde Eng. LLC
Sakarya Filyos Gas Development Field Project
Zonguldak / Türkiye
2022
He was responsible for the engineering design of various pile foundations and steel superstructures within the facility.
Rönesans Endüstri, TP-OTC, Schlumberger, Tecnicas Reunidas
Arctic LNG2 GBS Liquefied Natural Gas Container Structures Project
Murmansk / Russia
2021-2022
Participated in the engineering design of various steel structures within the facility.
Rönesans Endüstri-Saipem
Hardened Dormitory and Admin Buildings
Iraq
2019-2021
Preparation of buildings in accordance with American specifications (IBC, IPC, NFPA, IMC, AISC, ASCE, ACI) and OBO (Overseas Building Operations) requirements with BIM methodology, where civil, architectural, mechanical and electrical projects are created and coordinated by American certified professional engineers (PE) of all relevant disciplines.
Navigator International LLC
Jadriya Shopping Mall
Baghdad / Iraq
2020
The engineering design and detail project of the 3rd floor and roof steel system of the 10,000 m2 shopping mall was completed.
AM Tech LLC. - Dubai
Sefa Atakaş Technical and Anatolian Vocational High School, Shipbuilding Workshop
Iskenderun / Türkiye
2020
The construction, architecture, mechanical and electrical application and permit projects of the 4,200 m2 building were prepared within our scope. The construction and architectural projects were prepared at 3D and LOD350 detail level.
Atakaş Çelik Sanayi
Atakaş Steel Industry - Steel Service Center
Iskenderun / Türkiye
2019
Detailed design and analysis of the cutting equipment foundations and formwork and reinforcement projects were created by 3D modeling.
Atakaş Çelik Sanayi
Atakaş Port - Bulk Material Warehouse
Iskenderun / Türkiye
2018
The engineering design and consultancy works and coordination of the material warehouse consisting of 14,500 m2 retaining wall and steel roof were carried out.
Atakaş Port
Norm Asl Cement - Qızıldas Cement Factory
5000 tons / day
Baku / Azerbaijan
2018
Re-analysis of problematic existing structures, determination of damage mechanism and preparation of reinforcement projects.
- Tertiary air duct steel and reinforced concrete structures
- Air chamber steel structures (Clinker Cooling)
Norm Asl Çimento
Kuwait International Airport Terminal 2
Kuwait
2016 - 2018
Within the scope of the contractor company, project management and consultancy works of the terminal building and auxiliary facilities were carried out. The coordination of the construction projects was carried out via BIM. Some important services provided in the project;
- Establishing a project management system within the company
- Establishment of BIM management system within the company
- Establishing a corporate development system within the company
-Reinforced concrete and steel engineering project management
Limak, Fosters&Partners, Robert Bird, Aecom, Werner Sobek, GMW, Metta, PTD, Probe
Power Cement LTD. Line 3
7700 tons / day
Sindh / Pakistan
2017
Within the scope of this project, the design and detailing of the flour silo and spoiled clinker silos were made.
Post-tensioned Raw Meal Silo (D = 22.4 m, H = 73.8 m)
Broken Clinker Silo (D = 13 m, H = 33.75 m)
FLS, Prokon
Algerian Qatari Steel Iron and Steel Plant
2.000.000 t/year
Algeria
2016
The civil engineering services of the newly established iron and steel factory were carried out by the contractor company.
Danieli, Yenigün, Prokon
HENKEL Sulfonation Plant
Ankara / Türkiye
2015
The project management and engineering of the project was carried out within the contractor company on a turnkey basis. All disciplines and construction activities were directed and managed during the construction process of the project.
Türk Henkel, Prokon
MEDCEM 10,000 tons/day Cement Factory
Mersin / Türkiye
2014
Engineering studies for Packages A and C were carried out by the contractor company.
Aumund, FLSmidth, Claudius Peters, Prokon
Atakaş Flat Sheet Coldmill Complex
Iskenderun / Türkiye
2015
The project management, engineering and consultancy works of the newly established factory were carried out in all disciplines within the contractor company.
Danieli, Prokon
CIMPOR-YIBITAS (VOTORANTIM) Cement Plants
Sivas, Yozgat, Corum, Nevsehir / Türkiye
2013
Four closed clinker silos and clinker transport systems were designed and inspected in four facilities of Votorantim Cement; Votorantim Sivas, Votorantim Nevşehir, Votorantim Çorum and Votorantim Yozgat.
Cimpor Yibitas (Votorantim), Prokon
PHILSA-Philip Morris & SABANCI Cigarette Factory
Izmir / Türkiye
2013
The new NTM (New Tobaco Material) logistics building was designed with a multi-disciplinary approach, and project management and supervision were provided.
Philsa, Prokon
DELPHI Automotive Systems
Izmir / Türkiye
2011
Engineering, project management and supervision were carried out for the new 6250 m² production building and auxiliary facilities within the contractor company on the basis of all disciplines.
Delphi, Prokon
Ataturk Dormitory Campus Project
Istanbul / Türkiye
2012
The engineering works of the 110,000 m² dormitory were carried out by the contractor company in accordance with earthquake specifications.
IPKB, Prokon
Polysius, Prokon-Ekon '2007
FLSmidth '2012
Çimko 7500 tons/day Capacity Clinker Production Line
Kahramanmaras / Türkiye
2007, 2014
Large-scale buildings, some of which are listed below, were designed by the contractor company.
Coal Crushing Plant
2 Flour Silos (20,000 tons each)
Coal Mills and Bag Filters (2 units of 35 tons / hour)
Rotary Kiln Tertiary Air Ducts
Clinker Silo (250,000 tons)
Flour Mill and Bag Filters (3 units of 280 tons / hour)
3 Cement Mills with 180 tons / hour capacity
4 Cement Silos with a capacity of 20,000 tons
The static analysis of the preheater structure (130m) was repeated due to the capacity increase.
Carthage Djebel Ressas 5800 tons/day Cement Factory
Tunisian
2010-2011
Large-scale buildings, some of which are listed below, were designed by the contractor company.
Raw Material, Crushing, Transport and Storage
Additive Crushing, Receiving, Storage, Transportation
Homogenization Silo (Post-tensioned)
Coal Mill
Clinker Transport and Storage
Clinker Silo (Post- tensioned)
Broken Clinker Silo
Cement Mill (1 and 2),
Cement Silos (1, 2 and 3) (Post- tensioned)
Alternative Liquid Fuel Storage
Electrical Substations
Service Buildings (Workshop, Locker Room, Canteen, Administrative Building, Guardhouse)
FLSmidth, PEG S.A., Bureau Veritas, Prokon-Ekon
Mmk-Atakaş Iron & Steel Plant
(2,500,000 tons/year)
Iskenderun / Türkiye
2007-2010
Within the scope of the contractor company, project management, engineering and consultancy works of the newly established factory were carried out on the basis of all disciplines.
The engineering design of the reinforced concrete water tank with a volume of 3000+8000=11,000 tons was also made within the scope of this project.
Danieli, Prokon
850 MW Combined Cycle Power Plant
Gebze / Türkiye
2011
Engineering and control of reinforced concrete structures were carried out within the scope of the contractor company.
Ansaldo Energy, Prokon
Al Jabal Al Gharbi Water Supply
Libya
2009
Engineering and detailing of water tanks has been done.
Reinforced concrete water tank, Ar Rayayinah break pressure tank ( 13,000 tons)
Reinforced concrete water tank, Ar Ruhaybat regulating tank ( 27,000 tons)
MUŞ Cement Factory
Mus/ Türkiye
2008
Homogenized silo engineering and detailing works were carried out.
D=15m H=52.5m
Yurt Çimento, Teknik Yapı Proje
BAZIFA Cement Factory
7000 tons / day
Sulaymaniyah / Northern Iraq
2006
Within the scope of the contractor company, the design and detailing of many main structures, some of which are listed below, were carried out.
Post-tensioning raw meal silo
(D=20m, H=96m)
Post-tensioned clinker silo
(D=47m, H=22m),
Broken clinker silo and building
3 post-tensioned cement silos
(D=20m, H=84m)
UCC United Cement Corporation, Prokon
Alstom, Tekfen, Prokon
MARITZA Power Plant
Bulgaria
2006-2007
Within the scope of the contractor company, engineering management and control of reinforced concrete structures were carried out. Some of the main structures designed are listed below;
Bottom ash silo
Fly ash silo
Limestone silo
Reagent feed tank
Limestone preparation building
Limestone crusher building
Gypsum storage silo
Dough tank
Water treatment building
Ash water tank
Wastewater treatment building
Kardemir Iron and Steel Factory
Karabuk / Türkiye
2007
Within the scope of the contractor company, the design and detailing of the BOF (30,000m³) Gas Holder was carried out with a multidisciplinary approach.
SMS-Demag, Prokon-Ekon
Bogazliyan Sugar Factory
Yozgat / Türkiye
2006
Detailed engineering and control works of the factory with a sugar beet capacity of 10,000 tons/day were carried out.
Fives Cail, Maguin, Oyak-Ekon-Prokon
MB Eng. Services Ltd., Prokon
YAMAMA Cement Production Line
Riyadh / Saudi Arabia
2006
Isdemir Iron and Steel Factory
Iskenderun / Türkiye
2006
OG (60,000m³) Gas Holder design and detailing was carried out with a multidisciplinary approach.
10,000 tons/day
Within the scope of the contractor company, the design and detailing of many main structures, some of which are listed below, were carried out.
Post-tensioning raw meal silo
(D=20m, H=64m)
Post-tensioned clinker silo
(D=32m, H=48.3m)
2 bypass system steel silos
(D=6m, H=23.5m)
Detail design of dedusting system steel structures
Clinker cooling unit
Polysius, GAMA, Prokon